Work Order 20757

Type of work: 
Other
Other type of work: 
Air Compressors
Equipment: 
Describe the problem: 
Drain condensation from and wipe down air compressor tanks of air compressors in Pastry and Bread. Check oil sight and ensure adequate oil level.
Date requested: 
2026-08-26
Date received: 
2026-08-26
Status: 
Completed. Drained condensation from the bucket and wiped down the compressor with a damp rag. An oil change was completed for both compressors in the pastry department on 2026-08-29. The oil change for the bread department compressor is scheduled for November.
Completed: 
completed
Priority: 
High