User login
Username:
*
Password:
*
Request new password
Bakehouse Work Orders
Work Order 13484
Type of work:
Other
Other type of work:
re-caulk bakes toilets please
Equipment:
MISCELLANEOUS
Describe the problem:
Caulking is not holding well for the one, toilet is loose. Both need to be re-caulk.
Submitted by, name:
emily airhart
Submitted by, email:
[email protected]
Submitted by, department:
cleaning Dept
Date requested:
2023-04-04
Date received:
2023-04-04
Status:
complete
Completed:
completed
Priority:
Low
« Back