Work Order 12252
Type of work:
Other
Other type of work:
wire to water chiller
Equipment:
MISCELLANEOUS
Describe the problem:
wire came out when trying to clean the mold not sure where it is supposed to go
Submitted by, name:
Emily Airhart
Submitted by, email:
[email protected]
Submitted by, department:
Cleaning Dept
Date requested:
2022-08-15
Date received:
2022-08-15
Status:
put temp. wires back in position
Completed:
completed
Priority:
High